|
|
|
|
|
4.2.1P Manage Scope / Small Projects
Define Scope (4.2.1P.P1)
|
|
Role |
Scope Definition (Small Projects) |
|
1 |
Project Manager |
Collect requirements. The requirements provide further details regarding the nature of the deliverables. See 2.1.3.1P Collect Requirements for more information. |
|
2 |
Project Manager |
Verify scope. The scope must be verified (approved). This includes approval of the Project Charter and the business requirements. See 4.2.3.1P Verify Scope for more details. |
Control Scope (4.2.1P.P2)
Since small projects are much easier to define and they are usually completed very quickly, they typically do not have many change requests and those that do occur are generally scope change requests. If scope changes occur, they are typically also small in nature. The following simple process should be able to be performed quickly.
|
|
Role |
Scope Change Management (Small Projects) |
|
1 |
Project Manager, Team Member |
Identify scope change request Scope changes can be surfaced by anyone on the project team. They should be sent in writing to the project manager by paper, email, etc. No formal form is needed. |
|
2 |
Project Manager |
Validate it is a scope change The project manager validates that the request is, in fact, a scope change. |
|
3 |
Project Manager |
Determine the impact of the request The project manager determines the impact of the scope change to the project in terms of cost, effort and duration. If there are multiple viable options, the project manager determines the impact of the various options. |
|
4 |
Project Manager, Client Manager |
(Optional) Resolve small change requests if there is no impact on schedule and budget If the change request can be accommodated within the original project cost, effort and duration, the project manager and client manager have the flexibility to make the decision on whether the change should be approved. However, the sponsor must have agreed to delegate this responsibility – usually up to a certain threshold of cost or effort. |
|
5 |
Sponsor |
Take the information to the sponsor The appropriate analysis, impact and alternatives are taken to the project sponsor for resolution (if the request was not already approved in step 4 above). If the sponsor does not approve the request and the corresponding impact, the scope request is not pursued. |
|
6 |
Project Manager |
Add the incremental work (if any) to the schedule If the scope change request is approved, the appropriate activities are added to the schedule to ensure the change is implemented. |
|
7 |
Project manager |
Add incremental cost (if any) to the budget If the scope change request is approved, the incremental cost (if any) needs to be added to your project budget. |
|
8 |
Project Manager |
Communicate through your Status Reports The request, current status and resolution should be documented in the project Status Report. |



