|
|
|
|
|
3.1.3P Manage Issues / Large Projects
(3.1.3P.P1)
|
|
Role |
Manage Issues (Large Projects) |
|
1 |
Project Manager |
Identify the problem and document on the Issues Form Solicit potential issues from any project stakeholders, including the project team, clients, sponsors, etc. The issue can be surfaced through verbal or written means, but it must be formally documented using an Issues Form. |
|
2 |
Project Manager |
Determine if the problem is really an issue The project manager determines whether the problem can be resolved or whether it should be classified as an issue. |
|
3 |
Project Manager |
Enter the issue into the Issues Log If it is an issue, the project manager enters the issue into the Issues Log. |
|
4 |
Project Manager, Sponsor |
Determine who needs to be involved in resolving the issue The project manager determines who needs to be involved in resolving the issue. The sponsor may be involved, or the sponsor may not have the expertise to assist in the resolution process. For instance, the resolution may require technical or legal staff. The problem may be contractual and require resolution from the Purchasing Department. However, at some point the alternatives will be discussed and a resolution will be made. It is important to understand up-front who needs to be involved in making this final issue resolution. |
|
5 |
Project Manager, Team Member |
Assign to team member for analysis and alternatives The project manager assigns the issue to a project team member for investigation (the project manager could assign it to himself or herself). The team member will investigate options that are available to resolve the issue. For each option, the team member should also estimate the impact to the project in terms of budget, schedule and scope. |
|
6 |
Project Manager, Sponsor, Stakeholders |
Gain agreement on resolution The various alternatives and impact on schedule and budget are documented on the Issues Form. The project manager should take the issue, alternatives and project impact to the project sponsor and other appropriate stakeholders for discussion and resolution. The project manager may want to make a recommendation from among the alternatives as well. |
|
7 |
Project Manager |
Close the Issues Log The project manager documents the resolution or course of action on the Issues Log. |
|
8 |
Project Manager |
Close the Issues Form The project manager documents the issue resolution on the Issues Form and then closes and files this document. |
|
9 |
Project Manager |
Add action plan to the schedule Once a resolution is agreed upon, the appropriate corrective activities are added to the schedule to ensure the issue is resolved. |
|
10 |
Project Manager |
Update Charter, if necessary If the resolution of an issue causes the budget, effort or duration of the project to change, the current Project Charter should be updated. |
|
11 |
Project Manager |
Communicate through the Status Report The project manager communicates issue status and resolutions to project team members and other appropriate stakeholders through the methods established in the Communications Plan, including the project Status Report. |



